Construction is underway on a new amphitheater at Donald Anderson Park in Cornelia, with the project about 30% complete, City Manager Donald Anderson said. Charles Black Construction is handling the work.
The structure is beginning to take shape behind a construction fence. Concrete block work has been completed, and steel beams for the stage roof are being installed. Brick work is also planned as construction continues.
The contractor’s goal is to get the building enclosed before winter weather sets in. The project update listed April 7 as the target completion date.
The amphitheater will add a performance venue to Donald Anderson Park. Details about its future programming have not been announced.